Allied Gold CorporationKurmuk mine energized its power line and fed first ore to the crushing circuit, advancing commissioning and ramp-up toward first gold.

Allied Gold Corporation said the Kurmuk Mine in Ethiopia has energized its power line to the national grid and fed first ore through the crushing circuit as the project moves toward completing commissioning and transitioning to operations. The 88-kilometre, 132-kV power line and related substations were completed by Ethiopian Electric Power and now supply sufficient power to finish commissioning and advance ramp-up, under a 20-year power purchase agreement at a fixed rate of approximately US$0.04 per kilowatt-hour. Earlier this month first ore was delivered to the commissioned crushing circuit, and the full handover of that circuit from the commissioning team to the operations team is underway, with first ore expected in the grinding circuit in the coming weeks and first gold to follow soon thereafter. Mining continues to advance as planned, with an ore stockpile of approximately one million tonnes established and planned to grow to nearly 1.5 million tonnes, or three months of ore feed ahead of full circuit commissioning, initially from the Dish Mountain and Ashashire open pits. The mine holds 2.7 million ounces of Proven and Probable Mineral Reserves and is expected to produce 240,000 to 270,000 ounces in its first full year and approximately 300,000 ounces the following year, averaging at least 240,000 ounces per year over an initial 15-year mine life.
Allied Gold CorporationKurmuk mine energized its power line and fed first ore to the crushing circuit, advancing commissioning and ramp-up toward first gold.
China Nonferrous Mining Corp LtdEthiopian Electric Power completed the 88-km, 132-kV power line and substations supplying the Kurmuk mine under a 20-year PPA.