Meta Platforms Inc.Meta backs Texas/ERCOT data-center interconnection audit and commits to paying full energy and water costs, adding disclosure, grid, water and verification obligations that raise all-in cost per megawatt and can delay capacity

Texas Governor Greg Abbott ordered an audit on August 3 of projects moving through ERCOT's interconnection process, a queue containing more than 474 gigawatts of requests, over five times the state's record peak demand, and ERCOT began issuing verification requests on September 9. Meta said on August 10 that it would pay the full costs associated with its data centers' energy and water use rather than shift them to consumers, while Digital Realty welcomed the Texas framework on August 7. For Meta, a company generating tens of billions of dollars of cash can absorb infrastructure requirements that may make marginal projects harder to finance, though more disclosure, grid work, water obligations and project verification can push capacity further into the future and raise the all-in cost of each megawatt. Digital Realty benefits if its operating history, utility relationships and existing powered sites become harder to replicate, since scarcity can support rents and the value of developed capacity, but projects stuck behind transmission upgrades or compliance reviews can delay leasing and weaken development returns. Insider Monkey's database showed 254 hedge funds holding Meta in Q2 2026, down from 262 in Q1, while 73 funds held Digital Realty, up from 46, with D. E. Shaw increasing its position 43% to 1,542,316 shares; short interest in Digital Realty stood at 8.3 million shares on August 31, equal to 2.27% of float, with 3.97 days to cover.
Meta Platforms Inc.Meta backs Texas/ERCOT data-center interconnection audit and commits to paying full energy and water costs, adding disclosure, grid, water and verification obligations that raise all-in cost per megawatt and can delay capacity
Digital Realty Trust Inc
Abbott Laboratories