UBS Initiates Coverage on Five AI Data Center Stocks With Buy Ratings

โดย Investing.com·US·Read original
Summary · why it matters

UBS analyst Ryan Gravett initiated coverage of five AI data center colocation stocks with bullish ratings, citing rapid growth potential as artificial intelligence adoption accelerates and computing capacity remains constrained. In a September 22, 2026 research note, Gravett said these companies' legacy cryptomining operations have provided favorable grid access, already translating into approximately 5 gigawatts of leased capacity representing roughly $125 billion in contracted revenues. The analyst forecasts average annual EBITDA growth of approximately 80% across the coverage group from 2027 to 2029, about 10% above consensus estimates for 2029, and sees an average upside potential of 36% across the five stocks despite recent share price declines of around 45% from recent highs. The five names are Hut 8 Corp with a Buy rating and $143 price target implying 45% upside, Terawulf Inc with a Buy rating and $24 price target for 41% upside, Applied Digital Corp with a Buy rating and $38 price target for 35% upside, Core Scientific Inc with a Buy rating and $24 price target for 33% upside, and Cipher Mining Inc with a Buy rating and $23 price target for 25% upside.

Impact on assets 8

Artificial Intelligence▲ · 4 stocks
Cipher Mining Inc
CIFR
▲ PositiveCapitalrelevance

UBS initiated coverage with a Buy rating and $23 price target implying 25% upside.

Digital Finance & Tokenization▲ · 2 stocks
Terawulf Inc
WULF
▲ PositiveCapitalrelevance

UBS initiated coverage with a Buy rating and $24 price target implying 41% upside.

Aging Population▲ · 1 stocks
Financials▲ · 1 stocks

Theme Impact 2

Related news

5impact 4

Oracle Issues Force Majeure Notice on 2.45-Gigawatt Project Jupiter Site

Oracle has issued a force majeure notice for its 2.45-gigawatt site in Doña Ana County, New Mexico, named Project Jupiter, according to a Bloomberg report. The site is tied to the Stargate initiative with OpenAI and SoftBank, with OpenAI as the customer, and the notice was reportedly sent to the project's developer, private credit player Blue Owl Capital, as an attempt to delay payments if Project Jupiter fails to go online in 2028. Oracle vice president Michael Egbert said in a statement to Yahoo Finance that Project Jupiter remains on its planned schedule and that force majeure notices are commonplace in developments of this scale and do not by themselves establish a project delay or change delivery expectations. Oracle stock fell 4% on the news in Thursday's trading, and the development sent shares of Nvidia, AMD, and Micron lower. KeyBanc analyst Jackson Ader said Oracle is in the most tenuous cash position of all the major hyperscalers and that these types of issues might spread, though Oracle feels it more acutely than its larger, more cash-rich peers.
Yahoo Finance·1hRead more →
▼2

Oracle Sends Force Majeure Notice on New Mexico Data Center Project

Oracle fell 4.23% in premarket trading after Bloomberg reported that the company sent a force majeure notice to the developer of Project Jupiter, a massive data center being built in New Mexico. The developer is a unit of Blue Owl Capital, and the project has already run into local opposition and regulatory setbacks. Oracle is not trying to walk away as the site's main tenant, according to people familiar with the situation; instead, it aims to put off payments if the project is derailed and fails to come online in 2028 as planned, protecting itself from potential cost increases on the build. Companies typically invoke force majeure to free themselves from contractual obligations when problems arise beyond their control. The notice suggests Oracle sees a real risk the timeline slips, and it could shift part of that risk onto Blue Owl.
GuruFocus·4hRead more →
▼impact 4

Oracle Declares Unusual Force Majeure at New Mexico AI Data Center

Oracle is considering declaring force majeure on an AI data center project being built in New Mexico, according to a Bloomberg report. The project's developer is a unit of Blue Owl, a firm at the center of concerns over the private credit boom, and both Oracle and Blue Owl shares traded lower on the news. Oracle is not seeking to exit its role as the main tenant, but is trying to delay payments if the project is derailed and does not come online in 2028, in an effort to reduce its own financial liability and exposure. The force majeure reasoning cited is opposition and regulatory setbacks, which hosts noted is not a traditional force majeure declaration, since such clauses typically cover war, earthquakes, severe weather, or other acts of God outside a party's control. The hosts said it remains unclear from the report exactly what rationale underlies the declaration, and questioned whether regulatory setbacks could have been foreseen, a question courts may have to wrestle with.
Bloomberg·5hRead more →