Broadcom IncBroadcom provided about $29 billion in guarantees for a chip-purchasing vehicle leasing to Anthropic, adding off-balance-sheet risk if AI demand slows.
Technology companies have provided as much as $300 billion in guarantees for AI data centers and chips over the past year, according to the Financial Times, creating a financing structure that could change how investors assess the risks behind the artificial intelligence spending boom. The guarantees establish minimum future values for computing equipment or data centers owned by special-purpose entities, and if those assets later sell or lease for less than the guaranteed amount, the technology company could be responsible for part of the shortfall. Broadcom has provided about $29 billion in backing for a vehicle that will purchase chips and lease them to Anthropic, while Nvidia has agreed to support as much as 25% of certain infrastructure financing packages and provided $105 billion in guarantees tied to an Ohio data center campus for OpenAI. Meta has also provided a $28 billion guarantee for a data center venture with Blue Owl, and Morgan Stanley estimates seven major cloud and chip companies have accumulated more than $3.1 trillion in off-balance-sheet commitments and other credit support. Analysts generally view the underlying assets as sufficient collateral so far, but the equation could change if AI demand slows, equipment becomes obsolete faster or data-center capacity exceeds customer needs, leaving investors to watch whether AI infrastructure spending generates enough cash flow to support the financing structures behind the boom.
Broadcom IncBroadcom provided about $29 billion in guarantees for a chip-purchasing vehicle leasing to Anthropic, adding off-balance-sheet risk if AI demand slows.
NVIDIA CorporationNvidia agreed to support up to 25% of certain infrastructure financing packages and provided $105 billion in guarantees tied to an Ohio data center campus for OpenAI.
Meta Platforms Inc.Meta provided a $28 billion guarantee for a data center venture with Blue Owl, an off-balance-sheet commitment that could become a liability.
Morgan StanleyMorgan Stanley is cited only as the estimator of $3.1 trillion in off-balance-sheet commitments, not as a party exposed to the guarantees.
Blue Owl Capital IncBlue Owl is mentioned only as Meta's data center venture partner, with no detail on its own exposure or impact.