Huaibei Mining Holdings Co LtdUnit 1 of its subsidiary's coal-fired power project completed trial run and entered commercial operation, expanding coal-power integration scale and alleviating power supply tightness.

Huaibei Mining announced that Unit 1 of the 2×660MW ultra-supercritical coal-fired power generation project, constructed by its subsidiary Huaibei Juneng Power Generation Company, has successfully completed a 168-hour full-load trial run. All technical indicators met standards, and the unit has entered commercial operation. The project is a key supporting power source under Anhui Province's 14th Five-Year Plan for energy and power development, with a planned annual power generation of 5.94 billion kilowatt-hours. With Unit 1 now in service, both units of the project have been fully completed. Once fully operational, they will help alleviate the tight power supply-demand situation in Anhui and expand the company's coal-power integration scale.
Huaibei Mining Holdings Co LtdUnit 1 of its subsidiary's coal-fired power project completed trial run and entered commercial operation, expanding coal-power integration scale and alleviating power supply tightness.
Its Unit 1 completed 168-hour trial run and entered commercial operation, adding 5.94 billion kWh annual capacity and fully completing the project.