Cloud & Digital Infrastructure▲
Big Digital Energy and 10NetZero Complete Acquisition of Hood County, Texas Site
Big Digital Energy and 10NetZero have completed the acquisition of a power-ready industrial site in Hood County, Texas, through a 50/50 joint venture. The approximately 50-acre site, located less than 40 miles from Dallas-Fort Worth, currently has 17 megawatts of operational power and is expected to support a phased expansion to as much as 111 megawatts of grid capacity, subject to validation by ERCOT. Existing natural-gas infrastructure also provides the potential to add behind-the-meter generation, supporting a total buildout of up to 300 megawatts. Big Digital has engaged Northland Capital Markets as financial advisor to assess AI and HPC uses for its power assets and is in discussions with potential development partners and offtakers. The companies intend to advance site planning, engineering, and customer engagement for the proposed datacenter campus.