Blue Owl Capital CorporationBlue Owl unit received Oracle's force majeure notice, but Blue Owl says financial commitments to the multi-year project are unchanged.
Oracle has sent a force majeure notice to the developer of Project Jupiter, a Stargate data center campus in New Mexico, Bloomberg first reported Thursday. The notice would allow Oracle to delay payments should the facility miss its 2028 target to come online, though Oracle is not seeking to exit as the campus's main tenant. Blue Owl Capital, whose unit received the notice, said the notice does not change the financial commitments to the multi-year project. Oracle said Project Jupiter remains on its planned schedule and that it is fully committed to New Mexico. The campus, designed to handle 2.45 gigawatts, is meant to run on gas-powered fuel cells from Bloom Energy, and an Energy Transfer pipeline intended to deliver gas to the site has been delayed nearly six months, to Feb. 1, 2027, after regulators repeatedly denied permits. Project Jupiter is one of the flagship sites of Stargate, the AI infrastructure initiative Oracle, OpenAI and SoftBank announced with President Donald Trump early in his second term.
Blue Owl Capital CorporationBlue Owl unit received Oracle's force majeure notice, but Blue Owl says financial commitments to the multi-year project are unchanged.
Blue Owl Capital IncBlue Owl Capital's unit received the force majeure notice, though it says the project's financial commitments are unchanged.
Oracle CorporationOracle issued a force majeure notice allowing it to delay payments if the New Mexico Stargate campus misses its 2028 online target.
Energy Transfer LPEnergy Transfer's pipeline to the New Mexico Stargate site was delayed nearly six months after regulators repeatedly denied permits.
Bloom Energy CorpProject Jupiter's fuel-cell power supply is jeopardized by the force majeure notice and delayed gas pipeline, threatening Bloom Energy's role at the site.
Energy Transfer Partners L.P