Blue Owl Capital CorporationBlue Owl portfolio company Stack Infrastructure faces Oracle's force majeure notice on the $18B-loan-backed Project Jupiter data center, threatening the development's financing timeline.
Oracle has sent a force majeure notice to Stack Infrastructure, the developer of the massive New Mexico data center known as Project Jupiter, as it seeks to protect itself financially if the facility is delayed. Oracle is the main tenant of the project, which is being developed by Stack Infrastructure, a portfolio company of Blue Owl Capital, and is designed for 2.45 gigawatts of capacity, making it one of the larger facilities tied to the broader Stargate AI infrastructure buildout involving Oracle, OpenAI and SoftBank. According to Bloomberg, Oracle wants to defer payments if the site misses its planned 2028 opening, though it remains unclear whether the notice would release Oracle from any existing financial obligations. About 20 banks provided an $18 billion loan to support development of the campus, meaning any extended delay could affect more than just Oracle's occupancy timeline. The market reaction was immediate: Oracle shares fell about 4% in premarket trading, Blue Owl dropped roughly 4%, Bloom Energy, whose fuel cells are expected to help power the site, fell 5%, and SoftBank shares declined about 6%.
Blue Owl Capital CorporationBlue Owl portfolio company Stack Infrastructure faces Oracle's force majeure notice on the $18B-loan-backed Project Jupiter data center, threatening the development's financing timeline.
Blue Owl Capital IncBlue Owl Capital's portfolio company Stack Infrastructure received Oracle's force majeure notice on the Project Jupiter data center it is developing.
SoftBank, a partner in the Stargate AI buildout tied to Project Jupiter, saw shares decline as Oracle's force majeure notice clouds the data center's timeline.
Oracle CorporationOracle sent a force majeure notice to defer payments if the Project Jupiter data center misses its 2028 opening, signaling financial exposure to the delayed buildout.
SoftBank shares fell about 6% as its Stargate AI infrastructure buildout partner Oracle sent a force majeure notice on the Project Jupiter data center.
Bloom Energy CorpOracle's force majeure notice on Project Jupiter, whose fuel cells Bloom Energy is expected to supply, raises risk of delay to that power equipment demand.
Stack Infrastructure, developer of Project Jupiter, received a force majeure notice from main tenant Oracle, threatening deferred payments and the project's 2028 timeline.